July 28, 2024 (Sunday)
Time: | 07:00 AM to 08:00 AM (1 hour) |
Purpose: | A. Shutdown of Sultan Kudarat 69KV Bus to facilitate the following: 1. To tap the new DS03(5LI1SKU-SMY)SKU to 69kV Bus 1. 2. To energize the new SKU-SMY High Voltage Equipment without load. B. Shutdown of Kibawe – Sultan Kudarat 138KV line to facilitate replacement of insulator at Tower #8. C. Shifting of CLPC from Sultan Kudarat to Tacurong Substation |
Areas Affected: | Whole Cotabato Light Franchise |
Time: | 2:00 PM to 3:00 PM (1 hour) |
Purpose: | Normalization of Load: Shifting back of Cotabato Light loads from Tacurong Substation to Sultan Kudarat Substation. |
Areas Affected: | Whole Cotabato Light Franchise |